Link to Decision Summarized Download Summary in PDF Electricity – Rules Application The Alberta Electric System Operator (“AESO”) applied for approval of a revised adjusted metering practice (“AMP”) implementation plan for metering i.e. measuring electric energy that...
Search Results
These articles by our expert team cover the details of various decisions made by the Alberta Energy Regulator (AER), Alberta Utilities Commision (AUC), and Canada Energy Regulator (CER). Browse our searchable archive below to learn more about the results we’ve achieved for our clients.
FortisAlberta Inc. v. Alberta Utilities Commission, 2024 ABCA 110
Link to Decision Summarized Download Summary in PDF Statutory Appeal - Rates Application FortisAlberta Inc. ("Fortis") applied to the Alberta Court of Appeal (“ABCA”) for permission to appeal an Alberta Utilities Commission (“AUC”) generic cost of capital decision...
Alberta Electric System Operator Approval of Amended Alberta Reliability Standard COM-001-AB-3 and COM-002-AB-4, AUC Decision 28904-D01-2024
Link to Decision Summarized Download Summary in PDF Electricity – Rules Application The Alberta Electric System Operator (“AESO”) forwarded proposed changes to the Alberta reliability standards COM-001-AB-3 (Communications) and COM-002-AB-4 (Operating Personnel...
AUC Updates to Rule 007, AUC Bulletin 2024-06
Link to Bulletin Summarized Download Summary in PDF Facilities – Applications The AUC updated Rule 007: Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations, Hydro Developments and Gas Utility Pipelines (“Rule 007”) to align...
Pivotal Energy Partners Inc. Application for an Order Permitting the Sharing of Records Not Available to the Public Regarding the Bantry Power Plant and Parkland Power Plant, AUC Decision 28894-D01-2024
Link to Decision Summarized Download Summary in PDF Rates - Electricity Application Pivotal Energy Partners Inc. (“Pivotal Energy”) applied under s 3 of the Fair, Efficient and Open Competition Regulation (“FEOCR”), seeking permission to share records not available to...
ENMAX Power Corporation 2024 Annual Performance-Based Regulation Rate Adjustment, AUC Decision 28575-D02-2024
Link to Decision Summarized Download Summary in PDF Rates - Electricity Application ENMAX Power Corporation (“ENMAX”) submitted its 2024 annual performance-based regulation (“PBR”) rate adjustment filing pursuant to the provisions of the third generation PBR (“PBR3”)...
Amendments to Rule 027, AUC Bulletin 2024-05
Link to Bulletin Summarized Download Summary in PDF Power - Law The AUC amended Rule 027: Specified Penalties for Contravention of Reliability Standards ("Rule 027") to include the reliability standard PER-006-AB-1 (R1), assigning this standard a penalty category 2....
EPCOR Distribution & Transmission Inc. 2024 Annual Performance-Based Regulation Rate Adjustment, AUC Decision 28581-D02-2024
Link to Decision Summarized Download Summary in PDF Rates - Electricity Application EPCOR Distribution & Transmission Inc. (“EDTI”) submitted its 2024 annual performance-based regulation (“PBR”) rate adjustment filing pursuant to the provisions of the third...
ATCO Electric Ltd. 2024 Annual Performance-Based Regulation Rate Adjustment, AUC Decision 28570-D02-2024
Link to Decision Summarized Download Summary in PDF Facilities - Solar Application ATCO Electric Ltd. (“AE”) submitted its 2024 annual performance-based regulation (“PBR”) rate adjustment filing pursuant to the provisions of the third generation PBR (“PBR3”) plan. AE...
EPCOR Energy Alberta GP Inc. Updated 2024 Interim Regulated Rate Tariff Non-Energy Rates, AUC Decision 28457-D01-2024
Link to Decision Summarized Download Summary in PDF Rates – Rate Increase Application EPCOR Energy Alberta GP Inc. (“EPCOR”) applied for approval of its updated 2024 interim regulated rate tariff (“RRT”) non-energy rates. Decision The AUC approved EPCOR’s updated 2024...
FortisAlberta Inc. Application for Direction to Pay Compensation Related to Site Transfers, AUC Decision 28358-D01-2024
Link to Decision Summarized Download Summary in PDF Facilities - Value Application FortisAlberta Inc. (“Fortis”) requested the AUC to direct the transfer of electric distribution system assets from Battle River Power Coop REA Ltd. (“BRPC”) to Fortis, including the...
Enmax Corporation v Independent System Operator (Alberta Electric System Operator), 2024 ABCA 83
Link to Decision Summarized Download Summary in PDF Electricity - Appeal Application This was an appeal of a chambers judge decision (“Decision”) dismissing the originating application of ENMAX Corporation, ENMAX Energy Corporation and Calgary Energy Centre No. 2 Inc....
AUC Inquiry Into the Ongoing Economic, Orderly and Efficient Development of Electricity Generation in Alberta – Module A Report, AUC Decision 28501-D01-2024
Link to Decision Summarized Download Summary in PDF Electricity – Markets Application On August 3, 2023, the Government of Alberta (“GoA”) issued an order-in-council (“Order”) directing the AUC to hold an inquiry into the ongoing economic, orderly and efficient...
AUC Updates to the Hydro and Electric Energy Regulation, AUC Bulletin 2024-04
Link to Bulletin Summarized Download Summary in PDF Power - Law On March 6, the Alberta Utilities Commission (“AUC”) made updates to the Hydro and Electric Energy Regulation (“HEER”) to align it with the Electricity Statutes (Modernizing Alberta’s Electricity Grid)...
Updates to AUC Application Review Process Following Generation Approvals Pause, AUC Bulletin 2024-03
Link to Decision Summarized Rules – Applications Updates to AUC Application Review Process Following Generation Approvals Pause On February 29, 2024, the Generation Approvals Pause Regulation expired. This regulation prohibited the AUC from issuing approvals for new...
ATCO Electric Ltd. Kiwetinohk Opal Transmission Project, AUC Decision 28658-D01-2024
Link to Decision Summarized Electricity – Facilities Application ATCO Electric Ltd. (“AE”) applied for approval to construct and operate a new transmission line, a transmission line alteration and a connection to the approved Kiwetinohk Opal Gas Project. Decision The...
Alberta Electric System Operator Application for Approval of Amended Section 306.7 of the ISO Rules, AUC Decision 28081-D01-2024
Link to Decision Summarized Electricity - ISO Rules Application In this application, the AESO requested approval of; amendments to s 306.7 of the independent system operator (“ISO”) rules (“ISO Rules”), Mothball Outage Reporting; consequential amendments to s 2.4 of...
Amendments to AUC Rule 022: Rules on Costs in Utility Rates Proceedings and Rule 009: Rules on Local Intervener Costs, AUC Bulletin 2024-02
Link to Decision Summarized Rates – Proceeding Costs The AUC amended Rule 022: Rules on Costs in Utility Rates Proceedings (“Rule 022”), including the scale of costs, which governs the recovery of the costs of participation in rates proceedings before the AUC. The AUC...
London Economics International LLC Module B Study: Overview of Modeling Results and Key Findings Prepared for the Alberta Utilities Commission, AUC Proceeding 28542: AUC Inquiry Into the Ongoing Economic, Orderly and Efficient Development of Electricity Generation in Alberta
Link to Decision Summarized Market Development– Reliability Scope of Study The Government of Alberta directed the AUC to conduct an inquiry regarding the impact of the rising level of renewable energy on the Alberta electricity system, more specifically, the changes...
AUC Consultation on Proposed Rule Development for Emergency Billing Relief, AUC Bulletin 2024-01
Link to Decision Summarized Utility Billing - Rules The Alberta Utilities Commission (“AUC”) initiated a consultation process to incorporate requirements for emergency billing relief into a new rule to provide predictability and transparency for stakeholders. The AUC...
Enforcement Staff of the Alberta Utilities Commission Settlement Agreement with Avex Energy Inc., AUC Decision 28765-D01-2024
Link to Decision Summarized Enforcement - Facilities Application Enforcement staff of the AUC Enforcement Division (“Enforcement Staff”) applied for approval of a negotiated settlement agreement (“NSA”) between Enforcement Staff and Avex Energy Inc. (“Avex”) in...
TransAlta Corporation Pinnacle 1 & 2 Peaking Thermal Electric Power Project, AUC Decision 28464-D01-2024
Link to Decision Summarized Thermal Peaking - Facilities Application TransAlta Corporation (“TransAlta”) applied for approval to construct and operate a natural gas-fired thermal power plant (the “Power Plant”), including an associated substation, located within the...
Northstone Power Corporation Application for an Order Permitting the Sharing of Records Not Available to the Public Regarding the Elmworth Generation Station, AUC Decision 28781-D01-2024
Link to Decision Summarized Electricity - Markets Application Northstone Power Corporation (“Northstone”) applied pursuant to s 3 of the Fair, Efficient and Open Competition Regulation (“FEOCR”) seeking permission to share records not available to the public regarding...
AESO Application for Approval of Proposed Amendments to Section 306.4 of the ISO Rules, AUC Decision 28605-D01-2024
Link to Decision Summarized Electricity - ISO Rules Application The Alberta Electric System Operator (“AESO”) applied for approval of amendments to s 306.4, Transmission Planned Outage Reporting and Coordination of the Independent System Operator (“ISO”) Rules....
Alberta (Utilities Consumer Advocate) v FortisAlberta Inc., 2024 ABCA 12
Link to Decision Summarized Cost of Capital - Permission to Appeal Application The Office of the Utilities Consumer Advocate (“UCA”) sought status as a respondent, or alternatively as an intervener, in the applications filed by FortisAlberta Inc. and Apex Utilities...
2171802 Alberta Ltd. Bull Pound Solar Project Termination of Community Generation Designation, AUC Decision 28703-D01-2024
Link to Decision Summarized Solar Power – Generation Program Cancellation Application 2171802 Alberta Ltd., operating as Bull Pound Solar Partners (“BPSP”), requested that the AUC rescind the community generating unit designation for the 15-megawatt (“MW”) Bull Pound...
Direct Energy Marketing Limited Amendments to the Code of Conduct Regulation and Inter-Affiliate Code of Conduct Compliance Plan, AUC Decision 28623-D01-2024
Link to Decision Summarized Markets – Code of Conduct Compliance Application Direct Energy Marketing Limited (“DEML”) applied for approval of amendments to the Code of Conduct Regulation Compliance Plan of Direct Energy Regulated Services (“DERS”), Direct Energy...
ATCO Electric Ltd. Approval of Sale Offering for Narrows Point Power Plant, AUC Decision 28699-D01-2024
Link to Decision Summarized Electricity - Facilities Application ATCO Electric Ltd. (“AE”) applied for approval of a sale offering for isolated generating units CUL 483, CUL 429, CUL 430 and CUL 280 (“Isolated Units”) contained within its Narrows Point Power Plant...
City of Lethbridge 2024 Interim Transmission Facility Owner Tariff, AUC Decision 28671-D01-2024
Link to Decision Summarized Electricity - Rules Application The City of Lethbridge (“Lethbridge”) applied for approval of its 2024-2026 transmission facility owner (“TFO”) tariff and the 2024 TFO tariff on an interim and refundable basis. Decision In this decision,...
Enforcement Staff of the Alberta Utilities Commission Settlement Agreement with the Consumers’ Coalition of Alberta, AUC Decision 28648-D01-2023
Link to Decision Summarized Markets - Rules Application AUC enforcement staff (“Enforcement Staff”) and the Consumers’ Coalition of Alberta (“CCA”) applied for approval of a settlement agreement (“Settlement”) related to a disclosure of confidential information by the...
AUC Reconsideration of ATCO Electric Ltd. Z Factor Adjustment for the 2016 Wood Buffalo Fire, AUC Decision 28320-D01-2023
Link to Decision Summarized Electricity - Rates Application Previously, the Alberta Court of Appeal (“ABCA”) allowed ATCO Electric Ltd.’s (“AE”) appeal of the Alberta Utilities Commission (“AUC”) Decision 21609-D01-2019 (the “Z Factor Decision”) and returned the...
FortisAlberta Inc. 2024 Interim Performance-Based Regulation Rate Adjustment, AUC Decision 28576-D01-2023
Link to Decision Summarized Electricity - Rates Application FortisAlberta Inc. (“FortisAB”) applied for approval its third-generation performance-based regulation (“PBR3”) plan compliance filing and 2024 PBR annual rate adjustment application, as directed by the AUC...
EPCOR Distribution & Transmission Inc. 2024 Interim Performance-Based Regulation Rate Adjustment, AUC Decision 28581-D01-2023
Link to Decision Summarized Electricity - Rates Application EPCOR Distribution & Transmission Inc. (“EDTI”) submitted for approval its third-generation performance-based regulation (“PBR3”) plan compliance filing and 2024 PBR annual rate adjustment application, as...
ENMAX Power Corporation 2024 Interim Performance-Based Regulation Rate Adjustment, AUC Decision 28575-D01-2023
Link to Decision Summarized Electricity - Rates Application ENMAX Power Corporation (“ENMAX”) submitted for approval its third-generation performance-based regulation (“PBR3”) plan compliance filing and 2024 PBR annual rate adjustment application PBR, as directed by...
Alberta Electric System Operator 2024 Independent System Operator Tariff Update, AUC Decision 28627-D01-2023
Link to Decision Summarized Electricity - Rates Application The Alberta Electric System Operator (“AESO”) filed an application with the AUC, pursuant to ss 30 and 119 of the Electric Utilities Act (“EUA”), requesting approval of its 2024 update to the Independent...
ATCO Electric Ltd. 2024 Interim Performance-Based Regulation Rate Adjustment, AUC Decision 28570-D01-2023
Link to Decision Summarized Electricity - Rates Application ATCO Electric Ltd. (“AE”) submitted for approval its third-generation performance-based regulation (“PBR3”) plan compliance filing and 2024 PBR annual rate adjustment application, as directed by the AUC in...
Enfinite Corporation Application for an Order Permitting the Sharing of Records Not Available to the Public Regarding the eReserve 7, 8 and 9 Battery Energy Storage Power Plants, AUC Decision 28650-D01-2023
Link to Decision Summarized Wind Power - Markets Application Enfinite Corporation (“Enfinite”) applied pursuant to s 3 of the Fair, Efficient and Open Competition Regulation (“FEOCR”), seeking permission to share records not available to the public. The information...
Direct Energy Regulated Services 2024 Regulated Rate Tariff and Default Rate Tariff Interim Rates, AUC Decision 28661-D01-2023
Link to Decision Summarized Electricity - Rates Application Direct Energy Regulated Services (“DERS”) applied for approval of its 2024 regulated rate (“RRT”) and default rate tariff (“DRT”) interim rates. The proposed interim rates for 2024 were the same as the...
BA2 Wind GP Corp. Application for an Order Permitting the Sharing of Records not Available to the Public Regarding the Buffalo Atlee Wind Farm 2, AUC Decision 28602-D01-2023
Link to Decision Summarized Electricity - Records Application BA2 Wind GP Corp. (“BA2 Wind”) applied to the AUC under s 3(3) of the Fair, Efficient and Open Competition Regulation (“FEOCR”), seeking permission to share records not available to the public between BA2...
BA1 Wind GP Corp. Application for an Order Permitting the Sharing of Records Not Available to the Public Regarding the Buffalo Atlee Wind Farm 1, AUC Decision 28601-D01-2023
Link to Decision Summarized Electricity - Records Application BA1 Wind GP Corp., as general partner of BA1 Wind LP, (“BA1”) applied under the Fair, Efficient and Open Competition Regulation (“FEOCR”), seeking permission to share records not available to the public...
The City of Red Deer 2024 Interim Transmission Facility Owner Tariff, AUC Decision 28600-D01-2023
Link to Decision Summarized Electricity - Rates Application The City of Red Deer (“Red Deer”) applied to continue its currently approved 2023 transmission facility owner (“TFO”) tariff of $467,397 per month on an interim and refundable basis, effective January 1,...
NuVista Energy Ltd. Application for an Order Permitting the Sharing of Records Not Available to the Public Regarding the Wembley Thermal Power Plant, AUC Decision 28571-D01-2023
Link to Decision Summarized Electricity - Markets Application NuVista Energy Ltd. (“NuVista”) applied pursuant to s 3 of the Fair, Efficient and Open Competition Regulation (“FEOCR”), seeking permission to share records not available to the public regarding the...
Alberta Electric System Operator 2024 Balancing Pool Consumer Allocation Rider F, AUC Decision 28628-D01-2023
Link to Decision Summarized Rates - ISO Tariff Application The Alberta Electric System Operator (“AESO”) applied for approval of its 2024 Balancing Pool consumer allocation Rider F of $1.30 per megawatt hour (“MWh”). Decision The AUC approved the applied-for Rider F....
Alberta Electric System Operator Application for Revised Adjusted Metering Practice Implementation Plan and Related Amendments to Independent System Operator Tariff and Rules, AUC Decision 28441-D01-2023
Link to Decision Summarized Electricity - Tariffs Application The Alberta Electric System Operator (“AESO”) applied for approval of a revised implementation plan for its adjusted metering practice (“AMP”) and related amendments to the Independent System Operator...
ATCO Electric Ltd. Brintnell Area Fibre Optic Project, AUC Decision 28472-D01-2023
Link to Decision Summarized Electricity - Communication Application ATCO Electric Ltd. (“AE”) applied for approval to construct and operate a 13-kilometer (km”) overhead fibre optic cable between AE’s existing Brintnell 876S Substation and Alberta PowerLine General...
AltaLink Management Ltd. v. Alberta Utilities Commission, 2023 ABCA 325
Link to Decision Summarized Appeal - Procedural Fairness Appeal This was an appeal by AltaLink Management Ltd. (“AML”), ATCO Electric Ltd. (“AE”), ENMAX Power Corp. (“ENMAX”) and EPCOR Distribution and Transmission Inc. (“EDTI”) from the AUC’s decision to eliminate...
AECG Forty Mile Wind GP Corp. Forty Mile Wind Power Project Amendments, AUC Decision 27561-D05-2023
Link to Decision Summarized Wind Power - Safety Application RES Forty Mile Wind GP Corp (“RES”) applied to amend, construct and operate the previously approved Forty Mile Wind Power Project (the “Project”) and the Forty Mile 516S Substation. RES also applied to split...
ATCO Electric Ltd. Application for Orders Relating to the City of Lloydminster Annexation, Decision 28016-D01-2023
Link to Decision Summarized Electricity - Service Area Application ATCO Electric Ltd. (“AE”) applied to the Alberta Utilities Commission (“AUC”) for: confirmation of exclusive service area boundaries as determined by applicable Electric Distribution System Municipal...
ATCO Electric Ltd. Notice of Dispute for Micro-Generation, AUC Decision 28319-D01-2023
Link to Decision Summarized Solar Power - Micro-Generation Application Dale Sunderland, a “customer” under the Micro-Generation Regulation (“MGR”), submitted a micro-generation application to ATCO Electric Ltd (“AE”) proposing to build a 148.5-kilowatt (“kW”) solar...
ATCO Electric Ltd. Dog Rib Fibre Optic Connection Project, AUC Decision 28463-D01-2023
Link to Decision Summarized Communications - Facilities Application ATCO Electric Ltd. (“AE”) applied for approval to construct and operate the 185-meter (“m”) ELADFO021 underground fibre optic telecommunications cable, from AE’s existing Dog Rib 2082S Substation to...