Application

The City of Red Deer (“Red Deer”) applied to continue its currently approved 2023 transmission facility owner (“TFO”) tariff of $467,397 per month on an interim and refundable basis, effective January 1, 2024, until the AUC approves either a revised interim or a final tariff. Red Deer indicated that it is currently in the process of preparing a 2024 general tariff application but it did not anticipate that a final tariff would be in place before January 1, 2024.

Decision

The AUC approved the request for continuation of the currently approved tariff because: a final 2024 TFO tariff will not be approved and in place before January 1, 2024; and the interim rate promotes short-term rate stability and will allow for Red Deer’s rates to be trued-up to reflect the final 2024 TFO tariff once approved by the AUC.

Related Posts

Auer v. Auer, 2024 SCC 36

Auer v. Auer, 2024 SCC 36

Link to Decision Summarized Download Summary in PDF Appeal – Standard of Review What standard of review applies when we determine whether a regulation is established within the scope of the enabling...