Link to Decision Summarized Transmission Regulation - Section 19 Application On July 25, 2023, the Alberta Electric System Operator (“AESO”) forwarded a recommendation to the AUC, pursuant to s 19(4)(b) of the Transmission Regulation (“T-Reg”), to approve the new...
Search Results
These articles by our expert team cover the details of various decisions made by the Alberta Energy Regulator (AER), Alberta Utilities Commision (AUC), and Canada Energy Regulator (CER). Browse our searchable archive below to learn more about the results we’ve achieved for our clients.
ATCO Electric Ltd. – Transmission Line 7L65 Rebuild Project, AUC Decision 24102-D01-2020
Link to Decision SummarizedFacilities - Transmission In this decision, the AUC considered applications from ATCO Electric Ltd. (“ATCO Electric”) to construct a new single-circuit 144-kilovolt transmission line, designated as transmission lines 7L134 and 7L65, and to...
ENMAX Power Corporation – Highway 8 Transmission Line 138-7.82L Relocation Project, AUC Decision 24831-D01-2020
Link to Decision SummarizedFacilities - Transmission Line In this decision, the AUC considered an application from ENMAX Power Corporation (“ENMAX”) to alter and operate Transmission Line 138-7.82L near Highway 8 in the southwest quadrant of the City of Calgary. The...