Link to Decision SummarizedMarkets - EnforcementsApplicationTCB Welding & Construction Ltd. (“TCB”), a customer of ATCO Gas and Pipelines Ltd. (“AGP”), filed a complaint with AUC Enforcement staff (“Enforcement Staff”) concerning a delay in accessing a high-use...
Search Results
These articles by our expert team cover the details of various decisions made by the Alberta Energy Regulator (AER), Alberta Utilities Commision (AUC), and Canada Energy Regulator (CER). Browse our searchable archive below to learn more about the results we’ve achieved for our clients.
Mojek Resources Inc. Gage Bitcoin Mine Power Plant, AUC Decision 27527-D01-2023
Link to Decision SummarizedFacilities - ConsultationApplicationMojek Resources Inc. (“Mojek”) applied for approval to construct and operate a 96-megawatt natural gas-fired power plant designated as the Gage Bitcoin Mine Power Plant (the “Power Plant”). The application...
NOVA Gas Transmission Ltd. Application for Approval of Amendments to the NGTL Gas Transportation Tariff – Temporary Service Protocol, CER Decision RH-002-2019
Link to Decision SummarizedGas Transportation - Temporary Service Protocol In this decision, the CER considered NGTL’s Application (the “Application”) for approval of amendments to the NGTL Gas Transportation Tariff for the Temporary Service Protocol (“Protocol”). The...
ATCO GAS and Pipelines Ltd. Franchise Agreement with the Town of Drayton Valley (AUC Decision 24733-D01-2019)
Link to decision summarizedNatural Gas - Franchise Agreement In this decision, the AUC approved an application (the “Application”) made by ATCO Gas and Pipelines Ltd. (“ATCO”) on July 12, 2019, requesting approval of a natural gas franchise agreement (the ”Franchise...
Maritimes & Northeast Pipeline Management Ltd. Application for Approval of 2020-2021 Toll Settlement (NEB Letter Decision and Order TG-007-2019)
Link to decision summarizedNatural Gas - Toll Settlement In this decision, the NEB considered an application (the “Application”) from Maritimes & Northeast Pipeline Management Ltd. (“M&NP”) pursuant to Part IV of the National Energy Board Act and the Board’s...
Request for Regulatory Appeal by ISH Energy Ltd. of Approval Issued to Canadian Natural Resources Ltd. (AER Request for Regulatory Appeal No.: 1910998)
Link to decision summarizedRequest for Regulatory Appeal - Gas Over Bitumen - Request Denied In this decision, the AER considered ISH Energy Ltd. (“ISH”)’s request for a regulatory appeal of the AER’s decision to issue Approval 11475X to Canadian Natural Resources...
Evergreen Gas Co-op Ltd. – Franchise Agreement with the Town of Drayton Valley (AUC Decision 24257-D01-2019)
The AUC found that Clause 5(a)(ii) in the proposed franchise agreement relating to franchise fees was discriminatory and therefore not in the public interest. On that basis, the AUC declined to approve the franchise agreement as filed.
Westcoast Energy Inc. Application for the Spruce Ridge Program (NEB Decision GH-001-2018)
In this decision, the NEB considered Westcoast Energy Inc., carrying on business as Spectra Energy Transmission (“Westcoast”)’s application pursuant to section 58 of the National Energy Board Act (“NEB Act”) and section 43 of the National Energy Board Onshore Pipeline Regulations (“OPR”) for authorization to construct and operate the Spruce Ridge Program (the “Project”). The NEB found that it was in the public interest to approve Westcoast’s application to construct and operate the Project.
Nipigon LNG Corporation Application in respect of TransCanada PipeLines Limited and the TransCanada Mainline Pipeline System (NEB Letter Decision, OF-Tolls-Group1-T211-2018-01 01)
In this decision, the NEB considered Nipigon LNG Corporation (“Nipigon”)’s application for orders pursuant to sections 12, 13, 59, and 71 of the National Energy Board Act (“NEB Act”) directing TransCanada PipeLines Limited (“TransCanada”) to provide facilities, and service under just and reasonable terms, to connect and transport gas from the TransCanada Mainline pipeline system (the “TransCanada Mainline”) to Nipigon’s planned liquefied natural gas (“LNG”) project (the “Application”).
The NEB denied the Application.
Abandonment Hearing Many Islands Pipe Lines (Canada) Limited (NEB Decision MHW-001-2018)
In this decision, the NEB considered Many Islands Pipe Lines (Canada) Limited (“Many Islands”)’ application for the abandonment of the Renaissance – North Bronson Pipeline and associated facilities (the “Pipeline”).
Pursuant to paragraph 74(1)(d) of the National Energy Board Act (the “NEB Act”), and with consideration of section 50 of the National Energy Board Onshore Pipeline Regulations (the “OPR”), the NEB issued Order ZO-M182-005-2018 (the “Order”), granting Many Islands leave to abandon the Pipeline.
In this decision, the NEB considered Many Islands Pipe Lines (Canada) Limited (“Many Islands”)’ application for the abandonment of the Renaissance – North Bronson Pipeline and associated facilities (the “Pipeline”).
Pursuant to paragraph 74(1)(d) of the National Energy Board Act (the “NEB Act”), and with consideration of section 50 of the National Energy Board Onshore Pipeline Regulations (the “OPR”), the NEB issued Order ZO-M182-005-2018 (the “Order”), granting Many Islands leave to abandon the Pipeline.
Rebasing for the 2018-2022 Performance-Based Regulation Plans for Alberta Electric and Gas Distribution Utilities Second Compliance Proceeding (AUC Decision 23355-D02-2018)
In this decision, the AUC considered the second compliance filing for the interim notional 2017 revenue requirement and 2018 base K-bar for the 2018-2022 performance-based regulation (“PBR”) plans for the following Alberta electric and gas distribution utilities:
· AltaGas Utilities Inc.,
· ATCO Electric Ltd. (distribution),
· ATCO Gas and Pipelines Ltd. (distribution),
· ENMAX Power Corporation (distribution) (“ENMAX”),
· EPCOR Distribution & Transmission Inc. (distribution) (“EPCOR”), and
· FortisAlberta Inc. (“Fortis”)
(collectively, the “Distribution Utilities”).
While the AUC accepted the general principles and methodologies utilized by each of the Distribution Utilities for calculating their respective 2018 PBR rates, the AUC did not approve any specific rates in this decision since the directions throughout this and other decisions would result in changes to 2018 rates.
Applications for Review of Decision 22986-D01-2018, Compliance Application to Decision 22011-D01-2017, ATCO Pipelines 2017-2018 General Rate Application (AUC Decision 23539-D01-2018)
In this decision, the AUC considered applications by ATCO Pipelines, a division of ATCO Gas and Pipelines Ltd. (“ATCO Pipelines”) and the Office of the Utilities Consumer Advocate (“UCA”) for review of Decision 22986-D01-2018 regarding ATCO’s compliance application to Decision 22011-D01-2017, 2017-2018 General Rate Application (“the Decision”).
The Decision addressed a compliance filing from ATCO Pipelines, in Proceeding 22986, in accordance with the findings and directions provided in Decision 22011-D01-2017, in relation to ATCO Pipelines’ 2017-2018 general rate application (the “GRA Decision”).
The AUC granted ATCO Pipelines’ review application. The AUC found that the UCA did not meet the test for review. However, the AUC determined that a review, on its own motion, was warranted in relation to the issue of ATCO Pipelines’ accumulated depreciation balances.
NOVA Gas Transmission Ltd. Application for Construction and Operation of the Northwest Mainline Loop (NEB Decision GHW-001-2018)
On December 15, 2017, Nova Gas Transmission Ltd. (“NGTL”) applied to the National Energy Board (“NEB”) pursuant to section 58 of the National Energy Board Act (“NEB Act”), for authorization to construct and operate 23 kilometres of new pipeline within Clear Hills County, Alberta to transport sweet natural gas (the “Project”).
The NEB determined that it was in the public interest to approve NGTL’s application to construct and operate the Project.
NOVA Gas Transmission Ltd. Application for Approval of 2018-2019 Revenue Requirement Settlement and Final 2018 Rates, Tolls, Charges and Abandonment (NEB Letter Decision and Order TG-004-2018)
On 23 March 2018 NOVA Gas Transmission Ltd. (“NGTL”) filed an application for approval of the 2018-2019 Revenue Requirement Settlement (the “Settlement”) and Final 2018 Rates, Tolls, Charges and Abandonment Surcharges for the NGTL System (the “Application”).
The NEB approved the 2018-2019 Settlement, as filed as a package, and the applied-for final 2018 tolls and 2018 abandonment surcharges.
ATCO Gas, a Division of ATCO Gas and Pipelines Ltd. – Z Factor Application for Recovery of 2016 Regional Municipality of Wood Buffalo Wildfire Costs (AUC Decision 21608-D01-2018)
In this decision, the AUC considered ATCO Gas, a division of ATCO Gas and Pipelines Ltd.’s (“ATCO”) application to recover $11.199 million through a Z factor rate adjustment for the costs it incurred as a result of the 2016 Regional Municipality of Wood Buffalo wildfire (the “Wildfire”).
The AUC determined that:
(a) for 2016, all five of the criteria to qualify for a Z factor rate adjustment had been met;
(b) the Wildfire was of a similar nature and magnitude to other nature-related events identified in ATCO Gas’ 2009 depreciation study; and
(c) the Wildfire did not give rise to an extraordinary retirement of the destroyed assets.
Therefore, the depreciation expense associated with the assets that were replaced would continue to be recovered from ratepayers.
NOVA Gas Transmission Ltd. – North Montney Mainline Variance Application and Sunset Clause Extension Request (NEB Decision MH-031-2017)
The NEB found that there was a need for the facilities described in the Variance Application (the “NMML Facilities”) and that the NMML Facilities were economically feasible.
The Board found that approving NGTL’s existing tolling methodology for the NMML Facilities over the long-term would not result in just and reasonable tolls, due to the lack of adherence to the cost causation principle and goal of economic efficiency.
Bigstone Cree Nation v. Nova Gas Transmission Ltd. (2018 FCA 89)
In this decision, the Federal Court of Appeal (“FCA”) considered an application by Bigstone Cree Nation (“Bigstone”) for judicial review of Order in Council P.C. No. 2016-962 (the “Order”) made by the Governor in Council (the “GIC”) dated October 28, 2016. The Order directed the NEB to issue an environmental assessment decision statement concerning the 2017 Nova Gas Transmission Ltd. (“NGTL”) System Expansion Project in northern Alberta (the “Project”), and to issue the Certificate of Public Convenience and Necessity GC-126 (the “CPCN”) authorizing the construction and operation of the Project.
For the reasons summarized below, the FCA dismissed Bigstone’s application, finding that the Crown had adequately fulfilled its duty to consult and accommodate Bigstone.
Bashaw Oil Corporation – Applications for Proximity Critical Sour Wells Nisku Formation, Drayton Valley Area (AER Decision 2018 ABAER 002)
In this decision, the AER provided its reasons for denying Bashaw Oil Corp.’s (“Bashaw”) well applications 1842705, 1851246, and 1851250 and Water Act application 001-00400207 (the “Applications”), without prejudice to any future application.
ATCO Pipelines – Compliance Application to Decision 22011-D01-2017, 2017-2018 General Rate Application (AUC Decision 22986-D01-2018)
On August 29, 2017, the Commission issued Decision 22011-D01-2017, in which it directed ATCO Pipelines, a division of ATCO Gas and Pipelines Ltd. (“ATCO”) to file a compliance application in accordance with the findings and specific AUC directions set out in Decision 22011-D01-2017.
NEB Examination to Determine Whether to Undertake an Inquiry of the Tolling Methodologies, Tariff Provisions and Competition in Northeast British Columbia (NEB Examination Decision)
On January 26, 2017, the NEB Chairperson authorized Board Member L. Mercier to initiate an examination to determine whether an inquiry of the tolling methodologies or tariff provisions of one or more of the Group 1 NEB-regulated natural gas pipeline companies operating in Northeast BC was warranted.
Maritime & Northeast Pipeline Management Ltd. – Application for Approval of 2017-2019 Toll Settlement (NEB Decision RHW-003-2017)
In this decision, the NEB considered Maritime & Northeast Pipeline Management Ltd.’s (“M&NP”) application (the “Application”) for approval of its 2017-2019 Toll Settlement (the “Settlement”) for final tolls over the period 1 January 2017 through 30 November 2019 (the “Settlement Period”).
Maritime & Northeast Pipeline Management Ltd. – Application for Approval of 2017-2019 Toll Settlement (NEB Decision RHW-003-2017)
In this decision, the NEB considered Maritime & Northeast Pipeline Management Ltd.’s (“M&NP”) application (the “Application”) for approval of its 2017-2019 Toll Settlement (the “Settlement”) for final tolls over the period 1 January 2017 through 30 November 2019 (the “Settlement Period”).
NOVA Gas Transmission Limited – Application for the Sundre Crossover (NEB Decision and Order with Reasons to Follow GH-002-2017)
On 24 March 2017, NOVA Gas Transmission Ltd. (“NGTL”) applied to construct and operate the Sundre Crossover Project (the “Project”) pursuant to section 58 of the National Energy Board Act (“NEB Act”) and section 45.1 of the National Energy Board Onshore Pipeline Regulations (“OPR”) (the “Application”). In the Application, NGTL also requested exemptions from paragraph 30(1)(a) and section 31 of the NEB Act.
The Board approved the Project and issued Order XG-N081-030-2017, and associated conditions pursuant to section 58 of the NEB Act and section 45.1 of the OPR, respectively. The NEB granted NGTL the relief requested with respect to paragraph 30(1)(a) and section 31 of the NEB Act.
The NEB issued this decision with reasons to follow.
AER Decision Dismissing Request for Regulatory Appeal by Ken Cowles – Jupiter Resources Inc. Well Licences (Appeal No. 1849984)
In this decision, the AER considered Mr. Cowles’ requests under section 38 of the Responsible Energy Development Act (“REDA”) for regulatory appeals of the AER’s decisions to approve certain well licences (the “Licences”) issued to Jupiter Resources Inc. (“Jupiter”). The Licences were issued in December 2015, allowing Jupiter to drill and produce fourteen natural gas wells.
The AER determined that: (1) Mr. Cowles did not file a statement of concern in relation to the applications for which the Licences were issued; and (2) in any case, the record does not indicate that Mr. Cowles was directly and adversely affected by the AER’s decisions to issue the Licences.
The AER therefore dismissed the requests for regulatory appeals.
NOVA Gas Transmission Limited – Albersun Pipeline Asset Purchase Project (NEB Report GHW-001-2016)
On April 27, 2016, NOVA Gas Transmission Ltd. (“NGTL”) applied to the NEB seeking leave to purchase the Albersun Pipeline (the “Project”) from Suncor and include the cost in the NGTL System rate base, pursuant to Parts IV and V of the National Energy Board Act, and for a Certificate of Public Convenience and Necessity for the Albersun Pipeline, among other things, dated 27 April 2016.
The NEB granted NGTL leave to purchase the Project and approved NGTL’s request to include the purchase price of the Albersun Pipeline in the Alberta System rate base.
TransCanada PipeLines Limited – Application for Approval of Dawn Long Term Fixed Price Service (NEB Decision RH-003-2017)
On 26 April 2017, TransCanada PipeLines Limited (“TransCanada”) filed an application under Parts I and IV of the National Energy Board Act (“NEB Act”) (the “Application”), requesting the NEB approve:
(a) the Dawn Long Term Fixed Price (“LTFP”) service (the “Dawn LTFP Service” or “Service”);
(b) the tolling methodology and tolls for the Service; and
(c) consequential amendments to the Canadian Mainline Gas Transportation Tariff.
The NEB approved the Application as filed.
The NEB directed TransCanada to separately track and report annually the actual costs and revenues related to Dawn LTFP service and to provide, in all future toll proceedings, disaggregated information to support the prudence of Dawn LTFP service-related TBO costs.
AltaGas Utilities Inc. – 2016 Capital Tracker True-Up Application (AUC Decision 22710-D01-2017)
In this decision, the AUC considered AltaGas Utilities Inc.’s (“AltaGas”) 2016 capital tracker true-up application (the “Application”).
In this decision, the Commission made the following determinations:
-
because three projects, Drumheller Phase 6 (town), Settler Area 1 (town), and Erskine (rural) were not previously determined by the AUC to be needed, the AUC assessed these projects and found all three to be needed.
-
the actual scope, level, timing and actual costs of each of the projects or programs included in the 2016 true-up were prudently incurred and satisfied the project assessment requirement of Criterion 1.
-
the capital tracker projects or programs included in the 2016 true-up continued to meet the requirements of the accounting test under Criterion 1.
-
there was no need to reassess the project or program requirements against Criterion 2, unless the driver for the project or program had changed.
-
the projects or programs included in the 2016 true-up satisfied the materiality requirement under Criterion 3.
-
with one exception (discussed below), the AUC found that AltaGas complied with previous Commission directions.
NEB Reasons for Decision – Westcoast Energy Inc. Wyndwood Pipeline Expansion Project Application (GH-001-2017)
The NEB found the Project, as proposed by Westcoast, to be in the public interest and granted Westcoast’s requested orders to construct and operate the Project.
Direct Energy Regulated Services – Review of Decision 21568-D01-2016 (AUC Decision 22472-D01-2017)
The AUC found that it was reasonable to account for the cost of the funds over-collected from DRT customers, in establishing just and reasonable rates and to be consistent, it was also reasonable to consider the impact of the under-collection of funds from RRT customers over the same period. The AUC directed DERS to submit a compliance filing.
LNG Canada Development Inc. – Application to Extend Export Commencement Expiry Date, Licence GL-330
The NEB approved, pursuant to subsection 21(2) of the NEB Act and subject to GIC approval, the variance of Condition 3 of the Licence to reflect the 5-year extension to the expiry date for the commencement of exports.
Request for Regulatory Appeal and Suspension by Ember Resources Inc. – Encana Corporation and Manitok Energy Inc. (AER Appeal No.: 1885827)
The AER found that Ember is not directly and adversely affected by the decision to transfer the pipeline licences to Manitok. Therefore, the request for regulatory appeal was dismissed.
ATCO Pipelines – 2017-2018 General Rate Application (AUC Decision 22011-D01-2017)
The AUC directed that ATCO file a compliance filing in accordance with the findings and directions set out in the decision.
Alliance Pipeline Ltd. – Application for Clairmont Meter Station Decommissioning and Reclamation (NEB Abandonment Hearing MHW-003-2017)
The NEB granted Alliance leave to abandon the facilities, subject to conditions.
ATCO Utilities – Application for Review and Variance of the AUC July 20, 2017 Ruling (AUC Decision 20514-D01-2017)
The AUC dismissed the review application on the grounds that the Ruling was an interlocutory decision and the ATCO Utilities had not demonstrated special circumstances that would warrant granting review. The AUC further found that, in any event, the review application was moot, given the AUC’s subsequent decision to relieve the ATCO Utilities from the obligation to provide the directed information.
Canadian Natural Resources Limited – Request for Regulatory Appeal by Mike-Ro Farms Ltd.
The AER found that MRF was not directly and adversely affected by issuance of the Licence and therefore MRF was not eligible to request a regulatory appeal.
ATCO Utilities – 2014-2018 Pension Application (AUC Decision 21831-D01-2017)
The AUC directed ATCO Gas and Pipelines Ltd. to incorporate the findings of this decision in its compliance filing. The AUC directed ATCO Electric-Transmission to reflect the findings of this decision in its compliance filing.
TransCanada PipeLines Limited Application for Approval of Herbert Long Term Fixed Price Service (NEB Decision RH-002-2017)
Download ReportNatural Gas – TransCanada Mainline – Tolls and Tariff On 4 January 2017, TransCanada Pipelines Limited (“TCPL”) filed, under Parts I and IV of the National Energy Board Act (the “NEB Act”), an application for approval of a new long-term fixed price...
Tidewater Midstream and Infrastructure Ltd. Approvals – Regulatory Appeal Request by Partsch
The AER found that the Partschs failed to demonstrate that they were or might be directly and adversely affected by the Approvals. The AER therefore concluded that the Partschs were not an eligible person for the purposes of section 38(1) of REDA and dismissed the request for a regulatory appeal.
Tidewater Midstream and Infrastructure Ltd. Approvals – Regulatory Appeal Request by Sorenson
The AER held that the Sorensons had not demonstrated that they may be directly and adversely impacted by the Approvals and were therefore not an “eligible person” under REDA section 38.
ATCO Gas and Pipelines Ltd. – 2015 Capital Tracker True-up Application (AUC Decision 21843-D01-2017)
The AUC approved the 2015 K factor true-up refund of $2.9 million and $1.8 million in the north and south, respectively, the portions of the 2017 forecast K factor amounts of $0.8 million and $0.5 million in the north and south, respectively, arising from the approval of the 2017 updated SMR forecast, and the portion of the 2014 K factor amount associated with the Alberta Floods program of $0.375 million in the south.
Woodfibre LNG Export Pte. Ltd. Application for a 40-Year Licence to Export Natural Gas in the form of Liquefied Natural Gas (File OF-EI-Gas-GL-W157-2016-01 01)
The NEB decided to issue a 40-year Licence to Woodfibre, subject to Governor in Council approval, to export natural gas subject to the terms and conditions, included as an appendix to the decision.
ATCO Pipelines Request for Review and Variance of Decision 21515-D01-2016 (AUC Decision 22166-D01-2017)
The review panel found that ATCO Pipelines had not shown, either on a balance of probabilities or apparent on the face of the Original Decision, that an error in fact, law or jurisdiction had occurred on the basis of the above noted grounds that could lead the AUC to materially vary or rescind the Original Decision.
Westcoast Energy Inc. Application for Review of Decision re Toll Treatment of the Tower Lake Section (NEB Decision GH-003-2015)
The review panel concluded that that Westcoast had not raised a doubt as to the correctness of the TLS Tolling Decision on these grounds.
Direct Energy Regulated Services Application for Review of Decision 21568-D01-2016: Preliminary Question (AUC Decision 22282-D01-2017)
The AUC found that DERS met the first stage of the review and variance application (also referred to by the AUC as the “Preliminary Question”), the AUC allowed the review to proceed to stage two.
Letter Decision Approving AltaGas Application to Abandon the John Lake Pipelines (NEB Hearing MHW-003-2016)
The NEB concluded that subject to the conditions set out in the Order, approving the Application was in the public interest. The NEB therefore granted AltaGas leave to abandon the Pipelines.
ATCO Gas and Pipelines Ltd. (South)West Calgary Connector Pipelines Project (Decision 21591-D01-2017)
The AUC found that approval of ATCO’s application for the WCC project pipelines is in the public interest and should be approved subject to the conditions set out. The AUC found that the risk associated with the WCC project pipelines was acceptable and was satisfied that the pipelines can be operated safely.
Bonavista Energy Corporation: Regulatory Appeal of Well Licences and an Application for a Pipeline, 2017 ABAER 001
The AER denied BEC’s pipeline application. Given the AER’s finding that there was only a short term need for additional pipeline capacity, the AER held that short-term economic benefit to BEC did not justify the adverse impact to landowners. The AER’s ruling was on a without prejudice basis to BEC with respect to future projects.
2018-2022 PBR Plans for Alberta Electric and Gas Distribution Utilities (AUC Decision 20414-D01-2016)
In Decision 20414-D01-2016 (the “2016 PBR Decision”), the AUC determined the parameters that apply to the next generation of performance based regulation (“PBR”) plans. The parameters the AUC approved in the decision apply for the 2018-2022 PBR term.
TransCanada Mainline Tariff Amendment Application re Storage Transportation Service, Reasons for Decision (NEB Decision RH-001-2016)
The NEB denied TCPL’s application to amend the Mainline System tariff and eliminate STS-L.
NOVA Gas Transmission Ltd. – Towerbirch Expansion Project (NEB Decision GH-003-2015)
On September 2, 2015, NGTL filed an application with the NEB for approval of 87km of new gas pipeline and associated facilities’ in northwest Alberta and northeast British Columbia (the “Project”) to connect to the NGTL System.