by rlcAdmin | Jun 17, 2022 | Electricity
Link to Decision SummarizedElectricity – RatesApplicationIn this application, the Alberta Electric System Operator (“AESO”) submitted an application to finalize Rider L and stated that the collected amount exceeded the approved amount by $538,642.49. The AESO...
by rlcAdmin | Jun 14, 2022 | Electricity
Link to Decision SummarizedFacilities – ElectricityApplicationHilda Wind G.P. Inc. (“Hilda Wind”) and AltaLink Management Ltd. (“AML”) filed facility applications for the Hilda Wind Power Project Connection (the “Project”).DecisionUnder ss. 14, 15, and 19 of the...
by rlcAdmin | Jun 9, 2022 | Electricity
Link to Decision SummarizedFacilities – ElectricityApplicationTERIC Power Ltd. (“TERIC”) applied for approval to construct and operate the 20-megawatt (“MW”) eReserve5 Battery Energy Storage Power Plant Project (the “Power Plant”). DecisionThe AUC approved the...
by rlcAdmin | Jun 9, 2022 | Electricity
Link to Decision SummarizedElectricity – FacilitiesApplicationAltaLink Management Ltd. (“AML”) applied for a 240-kilovolt (“kV”) transmission line, designated as Transmission Line 1136L (“Line 1136L”). Line 1136L will be constructed from the Zachary 997S...
by rlcAdmin | Jun 9, 2022 | Electricity
Link to Decision SummarizedElectricity – AppealAppealENMAX Energy Corporation (“ENMAX”) and the Balancing Pool (together, the “Appellants”), appealed an arbitration award finding that Keephills Generating Unit #1 was offline for 216 days as result of force...