by rlcAdmin | Oct 27, 2023 | Electricity
Link to Decision Summarized Solar Power – Micro-Generation Application Dale Sunderland, a “customer” under the Micro-Generation Regulation (“MGR”), submitted a micro-generation application to ATCO Electric Ltd (“AE”) proposing to build a 148.5-kilowatt (“kW”)...
by rlcAdmin | Oct 27, 2023 | Gas
Link to Decision Summarized GAS- Rates Application In Decision 27084-D02-2023, the AUC determined the value of each of the base inputs to the formula, except the utility bond spread for the base period (“SPRDbase”). The AUC determined that it would use the average...
by rlcAdmin | Oct 27, 2023 | Gas
Link to Decision Summarized GAS – Rates Application The AUC initiates a mandatory review of cost-of-capital parameters every five years, subject to mid-term reopeners, on its own motion or upon application from interested parties. The cost-of-capital parameters...
by rlcAdmin | Oct 23, 2023 | Gas
Link to Decision Summarized Gas – Facilities Application ATCO Gas and Pipelines Ltd. (“AG”) applied for approval to construct and operate the Swanhills Loop Transmission Project, consisting of 4.6 kilometers (“km”) of new 168.3-millimeter (“mm”) high-pressure...
by rlcAdmin | Oct 20, 2023 | Gas
Link to Decision Summarized Gas – Facilities Application Trans Mountain Pipeline ULC (“Trans Mountain”) applied for approval of a deviation (“Deviation Application”) to the approved plan, profile and book of reference (“PPBoR”) in respect of certain lands in...