ENMAX Power Corporation – Victoria Park Transmission Line Relocation Project, AUC Decision 28001-D01-2023

Link to Decision Summarized

Facilities – Alteration

Application

NMAX Power Corporation (“ENMAX”) sought approval to relocate portions of the transmission lines in the Victoria Park area of southeast Calgary. ENMAX stated that its existing overhead 138-2.82L and 138-2.83L transmission lines are in conflict with the City of Calgary’s Green Line Light Rail Transit and 6th Street underpass projects.

Decision

The AUC approved the application for the reasons that will follow in a subsequent decision.