Approval Transfer
Application
BTG Power Corp. (“BTG”) and Horseshoe Power GP Ltd. (“Horseshoe”) filed applications with the AUC to transfer the approvals related to two power plants located near Nevis and Lacombe from Horseshoe to BTG. Transfer of the connection orders for the respective power plants is also sought. The proposed approval transfer relates to facilities previously approved by the AUC under Approval 22987-D02-2017 and Order 22987-D03-2017 regarding a 3.6-megawatt (“MW”) natural gas-fired power plant located near Nevis and connected to FortisAlberta Inc.’s distribution system and Approval 22987-D04-2017 and Order 22987-D05-2017 2017 regarding a 3.9-MW natural gas-fired power plant located near Lacombe and connected to FortisAlberta Inc.’s distribution system.
Decision
The AUC approved the requested power plant approval transfers outlined in the applications.
Applicable Legislation
Hydro and Electric Energy Act, RSA 2000, c H-16 – ss. 23.