EPCOR Distribution & Transmission Inc. 2022 Customer Specific Distribution Access Service and System Access Service Rate Update for Customer CS21, AUC Decision 27493-D01-2022

Link to Decision Summarized

Electricity Facilities – Rates

Application

Customer CS21, an existing customer of EPCOR Distribution & Transmission Inc. (“EPCOR”) in the customer specific (“CS”) rate class for customers with energy demands over 5,000 kVA, requested a service upgrade. The service upgrade was required because the customer elected to totalize its transmission demand supplied from two feeders connected to EPCOR’s POD12. Consequently, EPCOR applied to update the CS distribution access service (“DAS”) and system access service rates for Customer CS21.

Decision

The AUC approved EPCOR’s DAS rate CS21 of $573.90 per day, effective August 1, 2022. EPCOR was directed to true up any differences between the rate effective date and the 2022 actual cost of debt.

Related Posts

Auer v. Auer, 2024 SCC 36

Auer v. Auer, 2024 SCC 36

Link to Decision Summarized Download Summary in PDF Appeal – Standard of Review What standard of review applies when we determine whether a regulation is established within the scope of the enabling...