Facilities – Electricity
Application
TERIC Power Ltd. (“TERIC”) applied for approval to construct and operate the 20-megawatt (“MW”) eReserve5 Battery Energy Storage Power Plant Project (the “Power Plant”).
Decision
The AUC approved the application to construct and operate the Power Plant under s. 11 of the Hydro and Electric Energy Act (“HEEA”). The AUC approved the application to interconnect the Power Plant to the distribution system of FortisAlberta Inc. under s. 18 of the HEEA.
Applicable Legislation
Alberta Ambient Air Quality Objectives.
Alberta Utilities Commission Act, SA 2007, c A-37.2 – s 17.
AUC Rule 001: Rules of Practice.
AUC Rule 012: Noise Control.
Historical Resources Act, RSA 2000, c H-9.
Hydro and Electric Energy Act, RSA 2000, c H-16 -, s 11 and 18.
Pertinent Issues
In Decision 27234-D01-2022, the AUC approved the application to construct the eReserve5 Battery Energy Storage Project. The eReserve 5 Power Plant will be located directly adjacent to the eReserve5 Battery Energy Storage Project. The Power Plant consists of 11 1.9-MW lithium-ion battery modules from Tesla, Inc., with a total nameplate storage energy capacity of 20 MW-hours. The Power Plant will be located on 2.5 acres of privately-owned and previously cultivated land southeast of the town of Hardisty.
The AUC determined that the Power Plant complies with Rule 007: Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations, Hydro Developments and Gas Utility Pipelines, and Rule 012: Noise Control.
The AUC determined that the participant involvement program was adequate and that no outstanding concerns remained. The AUC accepted the environmental assessment report’s conclusion that the project lands include minimal habitat suitable for wildlife species.
The AUC accepted that, in the event of a fire, all emission concentrations would comply with applicable Alberta Ambient Air Quality Objectives guidelines at or beyond 100 meters of the Power Plant. The AUC found that the risk to health due to gases released in a fire is mitigated because the closest residence is approximately 750 meters away. The AUC noted that TERIC has an emergency response program (“ERP”) to support the development of its ERPs and imposed the following as conditions of approval:
(a) TERIC, and any subsequent operator, shall implement ongoing upgrades to improve the project’s safety, including but not limited to firmware and software enhancements, monitoring capability enhancement, process changes, and safety standards as they are developed; and
(b) TERIC, and any subsequent operator, shall continually update and improve the site-specific ERP, the corporate ERP, and associated ERPs and advise the local fire departments, including but not limited to incorporating all mitigation measures required from discussions with the local fire departments and input from interested stakeholders and residents.
The AUC also required that TERIC and any subsequent operator maintain insurance coverage sufficient to protect against any reasonably foreseeable liabilities.