Electricity – Rates
Application
EPCOR Energy Alberta GP Inc. (“EEA”) applied for approval of interim 2023 rates applicable to the non-energy regulated rates tariff (“RRT”).
Decision
The AUC approved EEA’s 2023 interim RRT non-energy rates, effective as of January 1, 2023.
Applicable Legislation
Electric Utilities Act, SA 2003, c E-5.1 – s 122.
AUC Rule 005: Annual Reporting Requirements of Financial and Operational Results.
Pertinent Issues
EEA indicated that it intends to file its 2023-2025 non-energy RRT application before the end of 2022. The AUC noted that the 2023-2025 application would not be decided before the beginning of 2023; as a result, the AUC determined for EEA to continue the approved 2022 non-energy rates on an interim refundable basis.