Solar Power – Facilities
Application
NU-E Corp (“NU-E”) filed a checklist application with the AUC to construct and operate the 8.75-megawatt (“MW”) Lethbridge 1 Solar Project (the “Power Plant”) on 40 acres of private, cultivated land in the city of Lethbridge. NU-E applied to connect the Power Plant to the City of Lethbridge Electric Utility’s distribution system.
Decision
The AUC approved the applications to construct, operate and connect the Power Plant.
Relevant Legislation
Alberta Utilities Commission Act, SA 2007, c A-37.2 – s 17.
Hydro and Electric Energy Act, RSA 2000, c H-16 – s 11.
AUC Rule 012: Noise Control.
AUC Rule 033: Post-approval Monitoring Requirements for Wind and Solar Power Plants.