Regulatory Law Chambers logo

EPCOR Distribution & Transmission Facility Owner Tariff, AUC Decision 27696-D01-2022

Link to Decision Summarized

Electricity – Rates

Application

EPCOR Distribution & Transmission Inc. (“EDTI”) applied for approval of its 2023 interim transmission facility owner (“TFO”) tariff. EDTI calculated its 2023 interim tariff as the sum of its approved 2022 TFO tariff and 50 percent of the difference between its applied-for 2023 final tariff and its approved 2022 tariff.

Decision

The AUC approved the application from EDTI for approval of its 2023 interim TFO tariff, effective January 1, 2023, on an interim refundable basis.

Applicable Legislation

Electric Utilities Act, SA 2003, c E-5.1 – s. 121(1) and (2), and 124(1).

Related Posts

Auer v. Auer, 2024 SCC 36

Auer v. Auer, 2024 SCC 36

Link to Decision Summarized Download Summary in PDF Appeal – Standard of Review What standard of review applies when we determine whether a regulation is established within the scope of the enabling...