Revised Date for Move of New Well Applications to OneStop, AER Bulletin 2019-24

Link to Bulletin Summarized

Bulletin – Well Applications


On October 3, 2019, the AER issued Bulletin 2019-22, announcing that all applications for new well licences would need to be submitted through OneStop as of October 17, 2019. This move was delayed and will now occur on November 7, 2019.

The Digital Data Submission system will stop accepting new well applications as of 5:00 p.m. on October 31, 2019, as a result of this transition to OneStop. A OneStop outage will be scheduled to implement the requisite changes.