Regulatory Law Chambers logo

NOVA Gas Transmission Limited – Application for the Sundre Crossover (NEB Decision and Order with Reasons to Follow GH-002-2017)

Download Report

Application to Construct and Operate Pipeline – Decision with Reasons to Follow


On 24 March 2017, NOVA Gas Transmission Ltd. (“NGTL”) applied to construct and operate the Sundre Crossover Project (the “Project”) pursuant to section 58 of the National Energy Board Act (“NEB Act”) and section 45.1 of the National Energy Board Onshore Pipeline Regulations (“OPR”) (the “Application”). In the Application, NGTL also requested exemptions from paragraph 30(1)(a) and section 31 of the NEB Act.

The Board approved the Project and issued Order XG-N081-030-2017, and associated conditions pursuant to section 58 of the NEB Act and section 45.1 of the OPR, respectively. The NEB granted NGTL the relief requested with respect to paragraph 30(1)(a) and section 31 of the NEB Act.

The NEB issued this decision with reasons to follow.

Related Posts