ENMAX Power Corporation 2016 Interim Transmission Tariff (Decision 21017-D01-2015)

Download Report

Interim Transmission Tariff


ENMAX Power Corporation (“ENMAX”) applied for approval of its 2016 interim transmission tariff by continuing its 2015 transmission tariff on an interim refundable basis, effective January 1, 2016 until such time as the AUC approves a revised interim or final 2016 transmission tariff.

ENMAX submitted that the AUC approved its 2015 transmission tariff in Decision 2014-347 and in Decision 20124-D01-2015, and that its 2015 transmission tariff was set to expire on December 31, 2015. ENMAX submitted that it intended to file a transmission tariff for 2016 and 2017 with the AUC in 2016. The AUC also issued Decision 20819-D01-2015 which varied paragraphs 34 and 35 of Decision 20124-D01-2015.

The AUC approved ENMAX’s request to continue with its 2015 transmission tariff on an interim and refundable basis. The AUC directed ENMAX to use the revised revenue requirements and resulting 2015 transmission tariff that was approved in Decision 20819-D01-2015 for the purposes of calculating the 2016 interim transmission tariff.

Related Posts

Auer v. Auer, 2024 SCC 36

Auer v. Auer, 2024 SCC 36

Link to Decision Summarized Download Summary in PDF Appeal – Standard of Review What standard of review applies when we determine whether a regulation is established within the scope of the enabling...