Regulatory Law Chambers logo

AltaGas Holdings Inc. Time Extension to Power Plant Approval 3547-D02-2015 (AUC Decision 21307-D01-2016)

Download Report

Time Extension – Facilities


AltaGas Holdings Inc. (“AltaGas”) submitted an application to the AUC for a time extension to construct the AltaGas Kent Energy Plant, a 95-megawatt natural gas fired power plant, with a 13.8/144-kilovolt step-up substation (the “Project”), located near Cold Lake, Alberta.

AltaGas originally received approval to construct the Project with a deadline of May 31, 2016 to complete construction. AltaGas requested a two-year time extension, arising from its extended discussions and consultations with the Cold Lake First Nations, and cited uncertainty related to the Government of Alberta’s Climate Leadership Plan. AltaGas noted that it would need additional time to evaluate potential impacts and reassess its investment decision in relation to the Project.

The AUC held that AltaGas has provided information on the need and duration for the extension and approved AltaGas’ request as filed.

Related Posts

Yatar v. TD Insurance Meloche Monnex, 2024 SCC 8

Yatar v. TD Insurance Meloche Monnex, 2024 SCC 8

Link to Decision Summarized Download Summary in PDF Administrative Law – Judicial Review v. Statutory Appeal Application Ummugulsum Yatar (“Ms. Yatar”) contested the denial of her insurance...