Link to Decision Summarized Download Summary in PDF Facilities – Environmental Application WR2 Wind GP Corp. and Wild Rose 2 Wind Inc. (collectively, “WR2”) filed an application with the Alberta Utilities Commission (“AUC”) for approval to amend the Wild Rose 2 Wind...
Search Results
These articles by our expert team cover the details of various decisions made by the Alberta Energy Regulator (AER), Alberta Utilities Commision (AUC), and Canada Energy Regulator (CER). Browse our searchable archive below to learn more about the results we’ve achieved for our clients.
Forty Mile Granlea Wind GP Inc. Application for an Order Permitting the Sharing of Records Not Available to the Public Regarding the Forty Mile Wind Power Project, Phase One, AUC Decision 28666-D01-2023
Link to Decision Summarized Wind Power - Markets Application Forty Mile Granlea Wind GP Inc. (“Forty Mile”) applied pursuant to s 3 of the Fair, Efficient and Open Competition Regulation (“FEOCR”), seeking permission to share records not available to the public...
Enfinite Corporation Application for an Order Permitting the Sharing of Records Not Available to the Public Regarding the eReserve 7, 8 and 9 Battery Energy Storage Power Plants, AUC Decision 28650-D01-2023
Link to Decision Summarized Wind Power - Markets Application Enfinite Corporation (“Enfinite”) applied pursuant to s 3 of the Fair, Efficient and Open Competition Regulation (“FEOCR”), seeking permission to share records not available to the public. The information...
BA4 Wind Gp Corp. Application for an Order Permitting the Sharing of Records Not Available to the Public Regarding the Buffalo Atlee Wind Farm 4, AUC Decision 28594-D01-2023
Link to Decision Summarized Wind Power - Markets Application BA4 Wind GP Corp. (“BA4 Wind”), applied pursuant to s 3 of the Fair, Efficient and Open Competition Regulation (“FEOCR”), seeking permission to share records not available to the public regarding the Buffalo...
AECG Forty Mile Wind GP Corp. Forty Mile Wind Power Project Amendments, AUC Decision 27561-D05-2023
Link to Decision Summarized Wind Power - Safety Application RES Forty Mile Wind GP Corp (“RES”) applied to amend, construct and operate the previously approved Forty Mile Wind Power Project (the “Project”) and the Forty Mile 516S Substation. RES also applied to split...
RES Forty Mile Wind GP Corp. Forty Mile Wind Power Project Amendments, AUC Decision 27561-D01-2023
Link to Decision Summarized Wind Power – Facilities Application RES Forty Mile Wind GP Corp. (“RES”) has prior approval to construct and operate a 398.5-megawatt (“MW”) wind power plant designated as the Forty Mile Wind Power Project, including the associated Forty...
TransAlta Coaldale Wind Inc. Tempest Wind Power Project, AUC Decision 27767-D01-2023
Link to Decision Summarized Wind Power - Facilities Application TransAlta Coaldale Wind Inc. (“TransAlta”) applied for approval to construct and operate the 99-megawatt (“MW”) Tempest Wind Power Plant and Tempest Substation (the “Project”). TransAlta also applied to...
Enerfin Energy Company of Canada Inc. Winnifred Wind Power Project, AUC Decision 26504-D01-2022
Link to Decision SummarizedWind Power - FacilitiesIn this decision, the AUC approved the applications from Enerfin Energy Company of Canada Inc. (“Enerfin”) for permission to construct and operate the 122.32-megawatt (“MW”) Winnifred Wind Power Plant (the “Power...
Bull Trail Renewable Energy Centre PG Inc. Bull Trail Wind Power Project, AUC Decision 26981-D01-2022
Link to Decision SummarizedWind Power - FacilitiesIn this decision, the AUC approved the application from Bull Trail Renewable Energy Centre GP Inc. (“Bull Trail Energy”) to construct and operate the 270-megawatt (“MW”) Bull Trail Wind Power Project (the...
Alberta Electric System Operator Needs Identification Document Application and ATCO Electric Ltd. Facility Application for Paintearth Wind Project Connection, AUC Decision 23206-D01-2021
Link to Decision SummarizedFacilities - Wind Power In this decision, the AUC approved the application for a needs identification document (“NID”) from the Alberta Electric System Operator (“AESO”) and the facility application from ATCO Electric Ltd. (“AE”) to connect...