Link to Decision Summarized Solar Power - Micro-Generation Application Dale Sunderland, a “customer” under the Micro-Generation Regulation (“MGR”), submitted a micro-generation application to ATCO Electric Ltd (“AE”) proposing to build a 148.5-kilowatt (“kW”) solar...
Search Results
These articles by our expert team cover the details of various decisions made by the Alberta Energy Regulator (AER), Alberta Utilities Commision (AUC), and Canada Energy Regulator (CER). Browse our searchable archive below to learn more about the results we’ve achieved for our clients.
Alberta Electric System Operator Needs Identification Document Application, AltaLink Management Facility Applications – Georgetown Solar Project Connection, AUC Decision 28327-D01-2023
Link to Decision Summarized Solar Power – Facilities Application Georgetown Solar Inc. (“Georgetown Solar”) has an AUC approval to construct the Georgetown Solar + Energy Storage Project (the “Power Plant”), which includes a solar power plant, a battery energy storage...
Aura Power Renewable Ltd. Decision on Preliminary Question Application for Review of Decision 27488-D01-2023 Burdett Solar Project, AUC Decision 28409-D01-2023
Link to Decision Summarized Solar Power – Review and Variance Application Aura Power Renewables Ltd. (“Aura”) applied for a review and variance of AUC Decision 27488-D01-2023, regarding the Burdett Solar Project (the “Decision”). Decision The AUC denied Aura’s...
Aura Power Renewables Ltd. Provost Solar Project, AUC Decision 27918-D01-2023
Link to Decision Summarized Solar Power - Facilities Application Aura Power Renewables Ltd. (“Aura Power”) applied for approval to construct and operate a 22.5-megawatt (“MW”) project designated as the Provost Solar Power Plant and to connect the power plant to the...
Sunnynook Solar Energy Inc. Sunnynook Solar+ Energy Storage Project, AUC Decision 27971-D01-2023
Link to Decision Summarized Solar Power – Facilities Application Sunnynook Solar Energy Inc. applied for approval to construct and operate the Sunnynook Solar+ Energy Storage Project (the “Project”), on approximately 828 acres of agricultural land in the Hanna area....
Greengate Power Corporation Luna Solar+ Project, AUC Decision 27843-D01-2023
Link to Decision Summarized Solar Power - Facilities Application Greengate Power Corporation (“Greengate”) applied for permission to construct and operate the Luna Solar+ Project (the “Project”) on approximately 5,624 acres of privately owned, cultivated land near the...