Link to Decision SummarizedFacilities - Solar Plant In this decision, the AUC approved an application from Elemental Energy Renewables Inc. (“Elemental Energy”) to alter the Chappice Lake Solar Project (the “Project”) by adding a 3.6-megawatt/10-megawatt hour battery...
Search Results
These articles by our expert team cover the details of various decisions made by the Alberta Energy Regulator (AER), Alberta Utilities Commision (AUC), and Canada Energy Regulator (CER). Browse our searchable archive below to learn more about the results we’ve achieved for our clients.
Aura Power Renewables Fox Coulee Solar Project Amendment, AUC Decision 25296-D01-2021
Link to Decision SummarizedFacilities - Solar Plant In this decision, the AUC approved the application from Aura Power Renewables Ltd. (“Aura”) to amend the previously approved 75-megawatt (“MW”) solar plant designated as the Fox Coulee Solar Project (the ”Power...
FortisAlberta Inc. Waterton Battery Energy Storage System, AUC Decision 26101-D01-2021
Link to Decision SummarizedReliability - Market In this proceeding, the AUC approved the application from FortisAlberta Inc. (“Fortis”) to construct and operate a battery energy storage system (the “System”) in Waterton Lakes National Park.DiscussionThe System...
Trans Mountain Pipeline ULC Trans Mountain Expansion Project Detailed Route Hearing MH-018-2020, CER Letter Decision
Link to Decision SummarizedPipelines - Route Hearing In this decision, the CER found that the detailed route proposed by Trans Mountain Pipeline ULC (“Trans Mountain”) for the Trans Mountain Expansion Project (“TMEP”) would be the best possible detailed route on the...
Nova Gas Transmission Ltd. Application to Construct and Operate the Edson Mainline Expansion Project, CER Report GH-001-2019
Link to Decision SummarizedPipeline Facilities In this Report, the CER discussed its recommendation, decisions, and reasons in respect of the application from NOVA Gas Transmissions Ltd. (“NGTL”) to construct and operate the Edson Mainline Expansion Project (the...
AESO Needs Identification Document Application, AltaLink Facility Application – Windrise Connection Project and Windy Flats 138S Substation Alteration, AUC Decision 25074-D01-2020
Link to Decision SummarizedNeeds Identification Document - Facility Application In this decision, the AUC considered four applications by three parties:Application 25074-A001 by the Alberta Electric System Operator (“AESO”) for approval of the needs identification...
Windrise Wind Energy Inc. – Transmission Line 497L and Interconnection, AUC Decision 25074-D02-2020
Link to Decision SummarizedFacilities - Transmission Lines In this decision, the AUC considered whether to approve Application 25074-A002 by Windrise Wind Energy Inc. to construct and operate a 138-kilovolt transmission line from Windrise 1063S Substation to Windy...
Hydro-Québec v. Matta, 2020 SCC 37
Link to Decision SummarizedTransmission Lines - Right of Way Agreements - Servitudes This decision involved a dispute regarding the applicability of servitude agreements entered into during the 1970s for the routing of a transmission line. The Supreme Court of Canada...
Dorin v EPCOR Distribution and Transmission Inc., 2020 ABCA 391
Link to Decision SummarizedAUC Jurisdiction In this decision, both a Majority (Crighton, J.A. and Pentelechuk J.A) and Minority (O’Farrall J.A.) of the Alberta Court of Appeal dismissed the appeal from Mark Dorin (the “Appellant”) on a question of law and/or...
Trans Mountain Pipeline ULC Trans Mountain Expansion Project Detailed Route Hearing MH-027-2020 – Phase 1, CER Letter Decision
Link to Decision SummarizedPipelines - Route Hearing In this letter decision, the CER found that, subject to the Phase 2 and 3 Hearings, the route proposed by Trans Mountain Pipeline ULC (“Trans Mountain”) would be the best possible detailed route of the Trans...
Westcoast Energy Inc. Doing Business As Spectra Energy Transmission Application to Construct and Operate the Silverstar Project, CER Letter Decision
Link to Decision SummarizedPipeline Facilities In this decision, the CER approved the application from Westcoast Energy Inc. doing business as Spectra Energy Transmission (“Westcoast”) to construct and operate the Silverstar Project (the “Project”).In the application,...
Trans Québec and Maritimes Pipeline Inc. Reinforcement and Asset Purchase Application, CER GH-001-2020
Link to Decision SummarizedPipelines, Asset Purchase, Construction and Operation In this decision, the CER approved an application from Trans Québec and Maritimes Pipeline Inc. (“TQM”) to purchase and operate the Sabrevois Assets owned by Énergir L.P (“Énergir”), as...
Coquitlam (City) v. British Columbia Utilities Commission, 2020 BCCA 289
Link to Decision SummarizedLeave to Appeal - Decommissioning - Pipelines - Jurisdiction In this decision, the City of Coquitlam (“City”) obtained leave to appeal a reconsideration decision (the “Reconsideration Decision”) of the British Columbia Utilities Commission...
Dow Fort Saskatchewan Industrial Complex Industrial System Designation and Ownership Transfer, AUC Decision 25696-D01-2020
Link to Decision SummarizedIndustrial System Designation In this decision, the AUC approved an application from Dow Chemical Canada ULC (“Dow”) for an industrial system designation (“ISD”) that encompasses all facilities at the Dow Fort Saskatchewan Industrial...
AltaLink Management Red Deer Area Transmission Development Decommission and Salvage of Remaining Portions of Transmission Lines 80L and 716L, AUC Decision 25140-D01-2020
Link to Decision SummarizedAUC Jurisdiction - Historical Resources In this decision, the AUC approved applications from AltaLink Management Ltd. (“AltaLink”) to decommission and salvage portions of transmission lines 80L and 716L.ApplicationsAltaLink filed...
Suncor Energy Inc. Base Plant Industrial System Designation Amendment, AUC Decision 25744-D01-2020
Link to Decision SummarizedIndustrial System Designation - Amendment In this decision, the AUC approved an application from Suncor Energy Inc (“Suncor”) to amend its Base Plant Industrial System Designation (“ISD”).IntroductionSuncor applied to amend the ISD to...
Alberta Electric System Operator Needs Identification Document Application, AltaLink Management Ltd. Facility Applications – Cascade Power Plant Connection, AUC Decision 25689-D01-2020
Link to Decision SummarizedNeeds Identification Document - Facility Application In this decision, the AUC approved the needs identification document (“NID”) application from the Alberta Electric Systems Operator (“AESO”) for the need to connect the Cascade Power Plant...
Nonroutine Commingled Abandonment, AER Bulletin 2020-20
Link to Bulletin SummarizedBulletin - Abandonment In this Bulletin the AER discussed nonroutine commingled abandonment. Any abandonment activity that varies from the requirements given in Directive 020: Well Abandonment, is considered “nonroutine” and must be approved...
BHE Canada Rattlesnake G.P. Inc, AltaLink Management Ltd. Rattlesnake Ridge Wind Power Project Facility Applications, AESO Needs Identification Document Application, AUC Decision 25018-D01-2020
Link to Decision SummarizedWind Power Plant Construction - Substation and Transmission Line Construction - Transmission System Access In this decision, the AUC approved facility applications from BHE Canada Rattlesnake G.P. Inc. (“BHE”) and AltaLink Management Ltd....
MÉTIS Corporation Métis Crossing Solar Project, AUC Decision 25634-D01-2020
Link to Decision SummarizedSmall Scale Generation Regulation In this decision, the AUC approved the application from Metis Economic Trade and Industrial Services Corporation (“MÉTIS Corp.”) to construct and operate a 4.86-megawatt (“MW”) solar power plant designated...
EPCOR Water Services Inc. – E.L. Smith Battery Energy Storage System, AUC Decision 25770-D01-2020
Link to Decision SummarizedAlteration of E.L Smith Solar Power Plant - Increasing Operational Performance In this decision, the AUC approved the application from EPCOR Water Services Inc. (”EPCOR Water”) for the alteration of a power plant designated as the E.L Smith...
TERIC Power Ltd. eReserve2 Battery Energy Storage Power Plant Project, AUC Decision 25691-D01-2020
Link to Decision SummarizedStand-Alone Battery Energy Storage Facility - Power Plant In this decision, the AUC approved the application from TERIC Power Ltd. (“TERIC”) to construct and operate the eReserve2 Battery Energy Storage Power Plant Project, and to...
Osum Production Corp. Orion Organic Rankine Cycle Power Plant, Industrial System Designation and Interconnection, AUC Decision 25517-D01-2020
Link to Decision SummarizedConditional Power Plant Approval - Industrial System Designation - Interconnection Application In this decision, the AUC approved the application from Osum Production Corp. (“Osum”) to construct and operate a power plant designated as the...
Akamihk Energy Incorporated Montana First Nation Solar Facility Community Generation Application, AUC Decision 25657-D01-2020
Link to Decision SummarizedSmall Scale Generation Regulation - Conditional Approval In this decision, the AUC qualified the Montana First Nation Solar Facility (the “Project”) as a community generating unit pursuant to Section 3 of the Small Scale Generation...
EPCOR Distribution & Transmission Inc., Disposition of the South Training Centre, AUC Decision 25443-D01-2020
Link to Decision SummarizedFacilities - Disposition Application In this decision, the AUC considered an application from EPCOR Distribution & Transmission Inc. (“EDTI”) for the disposition of its South Training Centre (“STC”). The AUC approved EDTI’s application...
EPCOR Distribution & Transmission Inc., Disposition of the South Training Centre, AUC Decision 25443-D01-2020
Link to Decision SummarizedFacilities - Disposition Application In this decision, the AUC considered an application from EPCOR Distribution & Transmission Inc. (“EDTI”) for the disposition of its South Training Centre (“STC”). The AUC approved EDTI’s application...
2113260 Alberta Ltd. Community Generation Designation for Oyen Community Solar Project, AUC Decision 24845-D04-2020
In this decision, the AUC considered whether to approve an application from 2113260 Alberta Ltd., operating as Oyen Solar Partners (“OSP”), to qualify its 15-megawatt solar power plant, designated as the Oyen Community Solar Project, as a community generating unit. The AUC approved the application and qualified the power plant as a community generating unit.
Alberta Power (2000) Ltd. and TransAlta Cogeneration Ltd. – Sheerness Power Plant Dual Fuel Conversion, AUC Decision 25546-D01-2020
In this decision, the AUC considered an application from Heartland Generation Ltd., on behalf of Alberta Power (2000) Ltd. and TransAlta Cogeneration Ltd. to alter the approval for the Sheerness Power Plant to allow for dual fuel operation (coal and natural gas) until January 31, 2023. The AUC approved the application.
Schuler Wind Energy GP Ltd. Schuler Wind Energy Centre Power Plant and 1017S Substation, AUC Decision 25439-D01-2020
Link to Decision SummarizedFacilities - Wind Power Project In this decision, the AUC considered whether to approve applications (the “Applications”) from Schuler Wind Energy GP Ltd. (“Schuler”) to construct and operate the Schuler Wind Energy Centre (the “Project”)...
Trans Mountain Pipeline ULC MH-048-2018 – Application for the Westridge Delivery Line Relocation, CER Letter Decision MH-048-2018
Link to Decision SummarizedFacilities - Pipelines - Indigenous Consultation The Westridge Delivery Line Relocation ApplicationOn 21 December 2017, Trans Mountain Pipeline ULC (“Trans Mountain”) filed an application with the National Energy Board (“NEB”) for an...
Alberta Health Services Foothills Medical Centre Power Plant, AUC Decision 23958-D01-2020
Link to Decision Summarized Facilities - Medical Centre Power Plant Expansion In this decision, the AUC considered whether to approve an application (the Application”) from Alberta Infrastructure (“AI”), on behalf of Alberta Health Services (“Alberta Health”), to...
Peavine Metis Settlement – 4.97-Megawatt Community Solar Power Plant, AUC Decision 25236-D01-2020
Link to Decision SummarizedFacilities - Solar Plant - Community Generation In this decision, the AUC considered applications from Peavine Metis Settlement (“Peavine MS”) to construct and operate a solar power plant designated as the 4.97-Megawatt Community Solar Power...
Fort McKay First Nation v. Prosper Petroleum Ltd., 2020 ABCA 163
Link to Decision SummarizedBitumen Recovery Project - Crown Consultation - Honour of the Crown In this decision, the Alberta Court of Appeal (“ABCA”) considered an appeal from the Fort McKay First Nation (“FMFN”) of the AER’s approval of an application by Prosper...
ATCO Electric Ltd. – Transmission Line 7L65 Rebuild Project, AUC Decision 24102-D01-2020
Link to Decision SummarizedFacilities - Transmission In this decision, the AUC considered applications from ATCO Electric Ltd. (“ATCO Electric”) to construct a new single-circuit 144-kilovolt transmission line, designated as transmission lines 7L134 and 7L65, and to...
ENMAX Power Corporation – Highway 8 Transmission Line 138-7.82L Relocation Project, AUC Decision 24831-D01-2020
Link to Decision SummarizedFacilities - Transmission Line In this decision, the AUC considered an application from ENMAX Power Corporation (“ENMAX”) to alter and operate Transmission Line 138-7.82L near Highway 8 in the southwest quadrant of the City of Calgary. The...
Heartland Generation Ltd. – Battle River Power Plant Amendment, AUC Decision 25493-D01-2020
Link to Decision SummarizedCoal Plant Conversion In this decision, the AUC considered an application from Heartland Generation Ltd. (“Heartland”) to amend the approval for the Battle River Power Plant to allow Unit No. 5 to operate as a dual fuel coal and natural gas...
Drumheller Solar Corporation – Drumheller Solar and Battery Storage Project, AUC Decision 25234-D01-2020
Link to Decision SummarizedFacilities - Solar - Battery Storage In this decision the AUC considered applications from Drumheller Solar Corporation (“DSC”) to construct and operate a solar power plant and a battery energy storage system designated as the Drumheller...
TransAlta Corporation – Keephills Power Plant Repowering, AUC Decision 25240-D01-2020
Link to Decision SummarizedCoal Plant Conversion In this decision, the AUC considered whether to approve an application from TransAlta Corporation (“TransAlta”) for the alteration of a power plant, designated as the Keephills Power Plant, by constructing and operating...
AltaGas Utilities Inc. Busby Pipeline System Project, Decision 25306-D01-2020
Link to Decision SummarizedFacilities - Gas Pipeline - Project Need In this decision, the AUC considered whether it was in the public interest to approve an application by AltaGas Utilities Inc. (“AltaGas”) for the Busby Pipeline System Project (the “Project”). The...
Alberta Electric System Operator – NID Application and EPCOR Distribution and Transmission Inc. – Facility Applications – West Edmonton Transmission Upgrade Project, Decision 23943-D01-2020
Link to Decision SummarizedNeeds Identification Application, Transmission Lines In this decision, the AUC approved a needs identification document (“NID”) application from the Alberta Electric System Operator (AESO”) and facility applications from EPCOR Distribution...
Capital Power Generation Services Inc. – Halkirk 2 Wind Power Project Time Extension, Decision 25047-D01-2020
Link to Decision SummarizedExtension of time - Wind farm requirements In this decision, the AUC granted Capital Power Generation Services Inc. (“Capital Power”) a time extension to construct the 148-megawatt wind power plant and associated substation designated as the...
C&B Alberta Solar Development ULC Tilley Solar Project – Amendment, Time Extension, Ownership Transfer and Connection Order, AUC Decision 24434-D01-2020
Link to Decision SummarizedFacilities - Amendment Application - Environment - Species at Risk, Wildlife Act In this decision, the AUC considered applications from C&B Alberta Solar Development ULC (“CBA”) to amend the previously-approved Tilley Solar Power Plant...
C&B Alberta Solar Development ULC Tilley Solar Project – Amendment, Time Extension, Ownership Transfer and Connection Order, AUC Decision 24434-D01-2020
Link to Decision SummarizedFacilities - Amendment Application - Environment - Species at Risk, Wildlife Act In this decision, the AUC considered applications from C&B Alberta Solar Development ULC (“CBA”) to amend the previously-approved Tilley Solar Power Plant...
Pattern Development Lanfine Wind ULC Lanfine Wind Power Project (AUC Decision 22736-D01-2020)
Link to Decision SummarizedFacilities - Wind Power Project In this decision, the AUC considered whether to approve applications from Pattern Development Lanfine Wind ULC (“Pattern”) requesting approval to construct and operate the power plant and substations,...
EDP Renewables SH Project GP Ltd. Sharp Hills Wind Project Amendments (AUC Decision 24401-D01-2019)
Link to Decision SummarizedWind Projects - Rule 012 - Noise Control In this decision, the AUC considered whether to approve applications from EDP Renewables SH Project GP Ltd. (“EDP”) for amendments to a power plant and substation, collectively designated as the Sharp...
Nova Gas Transmission Ltd. Application for North Central Corridor Loop, CER October 15, 2019 Letter Decision
Link to Decision SummarizedFacilities -Gas Pipeline In this decision the CER considered an application from Nova Gas Transmission Ltd (“NGTL”) for approval of its North Central Corridor Loop (North Start Section 1) Project (the “Project”). The CER approved the...
Aura Power Renewables Ltd. Empress Solar Power Plant, AUC Decision 23580-D01-2019
Link to Decision SummarizedFacilities - Solar Power Plant In this decision, the AUC considered whether to approve applications (the “Applications”) from Aura Power Renewables Ltd. (“Aura”) to construct and operate a solar power plant and to interconnect the power...
Abandonment Hearing Obsidian Energy Ltd. Application for Approval to Abandon One Lateral Pipeline (NEB Decision MHW-002-2019)
Link to decision summarizedNatural Gas - Lateral Pipeline Abandonment In this decision, the NEB considered an application (the “Application”), filed on September 25, 2019 by Obsidian Energy Ltd. (“Obsidian”) for leave to abandon an in-place pipeline (the “Project”)....
Aura Power Renewables Ltd. Fox Coulee Solar Project (AUC Decision 23951-D01-2019)
Link to decision summarizedSolar Power Plant - Facilities Application In this decision, the AUC considered whether to approve a power plant application (the “Application”) from Aura Power Renewables Ltd. (“Aura”) to construct and operate a 75-megawatt (MW) solar power...
AltaGas Holdings Inc. on Behalf of AltaGas Pipeline Partnership Application for Approval to Abandon the Pouce Coupe B Pipeline (NEB Decision MHW-005-2019)
Link to decision summarizedNatural Gas - Pipeline Project Abandonment In this decision, the NEB considered an application by AltaGas Holdings Inc. (“AltaGas”) on October 31, 2018 to abandon the Pouce Coupe B Pipeline Project (the “Project” or “Pipeline”) in-place (the...