Link to Decision SummarizedFacilities - ConsultationApplicationFortisAlberta Inc. (“FortisAB”) applied for an extension of the conditional exemption granted in Decision 23089-D01-2018 from section 7.2 of the FortisAlberta Inc. Inter-Affiliate Code of Conduct...
Search Results
These articles by our expert team cover the details of various decisions made by the Alberta Energy Regulator (AER), Alberta Utilities Commision (AUC), and Canada Energy Regulator (CER). Browse our searchable archive below to learn more about the results we’ve achieved for our clients.
Mojek Resources Inc. Gage Bitcoin Mine Power Plant, AUC Decision 27527-D01-2023
Link to Decision SummarizedFacilities - ConsultationApplicationMojek Resources Inc. (“Mojek”) applied for approval to construct and operate a 96-megawatt natural gas-fired power plant designated as the Gage Bitcoin Mine Power Plant (the “Power Plant”). The application...
External Engagement on Draft AUC Indigenous Consultation Framework, AUC Bulletin 2020-22
Link to Bulletin SummarizedBulletin - Indigenous Consultation Framework The AUC explained that it regulates the construction and operation of utility projects. The AUC has the authority to consider and address potential adverse impacts to Aboriginal and Treaty rights...
Trans Mountain Pipeline ULC MH-048-2018 – Application for the Westridge Delivery Line Relocation, CER Letter Decision MH-048-2018
Link to Decision SummarizedFacilities - Pipelines - Indigenous Consultation The Westridge Delivery Line Relocation ApplicationOn 21 December 2017, Trans Mountain Pipeline ULC (“Trans Mountain”) filed an application with the National Energy Board (“NEB”) for an...
Coldwater First Nation v Canada (Attorney General), 2020 FCA 34
Link to Decision SummarizedIndigenous Consultation This case involved applications for judicial review of the second approval by the Governor in Council (“GIC”) of the Trans Mountain Pipeline Project (the “Project”) following a reconsideration hearing before the...